During the demolition process, it was discovered all steel within the building had been coated with a primer containing lead during the initial construction in the mid 1960’s. This significantly impacted on the construction programme and extended the scope of works to include the encapsulation, extraction and urgent removal of lead affected areas. The work was further complicated and delayed by the Level 4 COVID-19 lockdown enforced in Auckland in August 2021.
Management and removal of the lead primer became a very expensive and drawn-out process, with the implementation of lead contamination protocols such as capturing all airborne contaminants from the manual scraping and removal of the affected primer and the requirement for decontamination showers, PPE and additional manpower for the manual removal method initially adopted.
The Level 4 lockdown in August 2021 put a halt to all works on site. Once Auckland was moved to Alert Level 3, contractors were allowed back on site but working under strict Covid-19 safety protocols with restrictions on the number of contractors able to be on site at any given time, and additional PPE and precautionary protocols put in place and stringently adhered to.
InterGroup investigated and offered an alternate removal process to assist the client in mitigating the cost and time impact to the project of continuing the manual lead primer removal process. We introduced the use of a revolutionary paint removal system specifically formulated product designed to remove multiple layers of paint in one application. The product was applied to the steel components, encapsulating, lifting, and removing the lead primer. The use of this system meant a reduction in the level of management required to remove contaminants, providing cost and time efficiencies for the client by reducing the labour requirement and encapsulation costs.